Learn, Practice, and Improve with SAP C_S4CCO_2506 Practice Test Questions
- 80 Questions
- Updated on: 3-Mar-2026
- SAP Certified Associate - Implementation Consultant - SAP S/4HANA Cloud Public Edition, Management Accounting
- Valid Worldwide
- 2800+ Prepared
- 4.9/5.0
Production Accounting (F2261, F2262, F2271)
In by order, which production order status triggers work in progress (WIP) at actual cost?
Note: There are 3
Correct Answers to this question.
A. Delivered
B. Partially Released
C. Technically Completed
D. Released
E. Partially Delivered
D. Released
E. Partially Delivered
Which of the following variance categories are available in SAP S/4HANA Cloud Public Edition?
Note:
There are 3 Correct Answers to this question.
A. Output price variance
B. Resource usage variance
C. Input price variance
D. Lot size variance
E. Scrap variance
C. Input price variance
E. Scrap variance
What do you need to configure in order to be able to allocate project costs based on their origin?
A. PA Transfer structure
B. Source structure
C. Allocation structure
D. WBS structure
In a make-to-order scenario with event-based, how are variances calculated?
Note: There are 2 Correct
Answers to this question.
A. Production variances are automatically calculated
B. Production variances can also be calculated in case of partial delivery
C. Production variance calculation can always be triggered manually on demand
D. Production variances are calculated if an order has the status DELIVERED
B. Production variances can also be calculated in case of partial delivery
When using repetitive manufacturing, on which cost object do you track the costs?
A. Process order
B. Production order
C. Service order
D. Product cost collector
Where do you define whether down payments are taken into account during settlement?
A. Settlement Profile
B. Settlement Rule
C. Distribution Rule
D. Source Structure
How are target costs calculated for a production order?
A. Planned costs are adjusted for the actual lot-size when doing a goods receipt on the order.
B. Planned costs are adjusted for the actual lot-size when doing a goods issue on the order.
C. Planned costs are adjusted for the planned lot-size when doing a goods issue on the order.
D. Planned costs are adjusted for the planned lot-size when doing a goods receipt on the order.
| Page 5 out of 12 Pages |