Learn, Practice, and Improve with SAP C_TS412_2021 Practice Test Questions
- 30 Questions
- Updated on: 13-Jan-2026
- SAP Certified Application Associate - SAP S/4HANA Project Systems
- Valid Worldwide
- 2300+ Prepared
- 4.9/5.0
Stop guessing and start knowing. This SAP C_TS412_2021 practice test pinpoints exactly where your knowledge stands. Identify weak areas, validate strengths, and focus your preparation on topics that truly impact your SAP exam score. Targeted SAP Certified Application Associate - SAP S/4HANA Project Systems practice questions helps you walk into the exam confident and fully prepared.
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
A. Use an offset of two days for the relationship of both activities.
B. Use an offset of two days for milestone date.
C. Use an offset of two days for the requirement date of the material component
D. Calculate the start date of the activity and set the constraint 'Must start on' accordingly.
D. Calculate the start date of the activity and set the constraint 'Must start on' accordingly.
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ... What is the typical sequence for the following business transactions and document?
A. Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..
B. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.
C. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.
D. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.
How can the system activate requirements (such as reservations or purchase requisitions)?
A. Immediately, by saving the project
B. Automatically, using the requirement date and the replenishment lead time
C. Using a standard milestone activity
D. When releasing a network or an activity
D. When releasing a network or an activity
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement scheduling of events?
A. Priority of events must be set.
B. Scheduling parameters for material scheduling must be set.
C. Events must be released manually.
D. Event scenarios must be defined
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
A. You can create several WBS elements per level.
B. A new work breakdown structure must contain up to 10 levels.
C. A WBS element of the new project can be assigned to a different project definition.
D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
E. The WBS structure can contain several level 1 WBS element
C. A WBS element of the new project can be assigned to a different project definition.
D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?
A. Standard WBS elements
B. Network header for activity-account-assigned networks
C. WBS elements
C. WBS elements
You are working with networks and WBS elements. Which of the following statements applies
A. You can reassign an activity from one network to another
B. You can assign the network header to multiple WBS elements
C. You have to maintain a network profile in the project profile
D. You have to activate the operative indicator Account Assignment Element for WBS element with activities.